TIP Amendment to City of Grand Rapids College Avenue Project
The City of Grand Rapids has requested to increase the local share of funding on their FY2022 College Avenue reconstruction project from Leonard to Sweet, which will increase its total budget by more than 25% of the original federally approved budget. The federal funding will not change, and no other projects in the Transportation Improvement Program will be impacted. See below for details.
Original Budget
Federal Funding - $725,926
Local Participating Funding - $242,824
Total Participating Budget - $968,750
Non-participating Budget - $1,750,000
Final Budget
Federal Funding - $725,926
Local Participating Funding - $1,318,264
Total Participating Budget - $2,044,190
Non-participating Budget - $1,391,069
If you have any questions or comments, please email Laurel Joseph at laurel.joseph@gvmc.org